ClickCease

How Long Does It Take to Remodel a Kitchen

11/23/2022

Whether you want more space or a whole new build for your Kitchen, remodeling is always preferable. Kitchens are the places that are primarily used among the rooms of the house, so they need regular maintenance.

Kitchen remodeling is a lengthy process because it involves several things to consider. Therefore, having a clear idea of the time needed for kitchen remodeling will help you manage your resources effectively.

The article discusses how long it takes to remodel a kitchen for average-sized Kitchens in the Cleveland. Therefore, without further ado, let's dive straight into it.

Kitchen Remodeling Timeline

The average timeline for kitchen remodeling in the Cleveland is about 6 - 8 weeks. You must hire a professional with extensive experience in installation, plumbing, and electrical renovation.

Notably, if you do kitchen remodeling by yourself, it may take longer because it involves some complexities which may be tough to handle. Therefore, we always recommend that hiring professionals complete this task effortlessly.

The duration may vary based on the requirements. Here are the average estimates for the remodeling schedule.

  • A simple kitchen makeover takes about 7 - 8 weeks.
  • The complex refurbishing involves changing the layout and takes 10 - 12 weeks.
  • A whole new build may take longer, about 3 - 5 months.

Why Are Kitchen Remodels So Time-Consuming?

Kitchen remodeling takes time because it involves plenty of elements, such as extensive plumbing, heating, electrical wiring, a sturdy cabinet set, proper countertops, long-lasting flooring, and all built-in appliances (ovens, microwaves, and so on).

Before remodeling, you must clean the existing space, which can be tricky if you change the layout of the ovens and sink. Therefore, it must be planned appropriately so you can use that area effortlessly. As a result, the timeline for kitchen remodeling is usually longer than other rooms.

Breaking Down Your Kitchen Renovation Timeline

The Kitchen Remodeling process varies based on the details you want and the intricacy involved in the installation. We've listed different elements in the kitchen remodeling along with the needed time.

  • Planning Phase - 3 to 4 Weeks
  • Ordering Materials - 1 to 2 Months
  • Kitchen Removal - 2 to 3 Days
  • Structural Changes- 1 to 3 Months
  • Floor Installation - 2 to 7 Days
  • Cabinet Installment - 2 to 7 Days
  • Fixture and Appliance Installation - 1 to 5 Days
  • Countertop Installation - 1 to 3 Days
  • Backsplash and Tiling - 1 to 3 Days

These are the features usually involved in Kitchen Remodeling, and the duration varies depending on the requirement.

Start Your Project Today!

Now you have a clear idea about "How long does it takes to remodel a Kitchen?" and can start your project by distributing the proper time based on the details and features you need. As discussed above, the average duration needed for kitchen remodeling is about 6 - 8 weeks.

Get your Kitchen Remodeling done by the top kitchen remodeling service providers in Cleveland. We've discussed all the guidelines for renovating your house on a budget and within minimal time.